Since the plastering has taken place in the kitchen, we have continued these works throughout. The living room, sun lounge/dining area and hall have now been fully plastered in preparation for decoration. During this time the kitchen has also began the installation process, which has consisted of the following:
- Templated units for siltstone worktop
- Installation of base units and wall units
- Supply and fit worktop including cut out for Belfast sink and hole
- Supply and fit appliances within the kitchen: Microwave, Double Oven, Wine Fridge, Hob and Dishwasher